- Name
- Bosbury and Catley Group Neighbourhood Development Plan
- Parishes in neighbourhood area
- Bosbury (part of)
- Current stage
-
The Neighbourhood Development Plan is adopted.
- Dates of each stage
-
- Neighbourhood area application date: 8 June 2014
- Designation date: 1 August 2014
- Regulation 14 draft plan submitted: 18 December 2014
- Regulation 16 plan submitted: 6 March 2015 (withdrawn), 9 November 2016 (re-submitted), 8 June 2018 (second re-submission)
- Plan sent for examination: 17 January 2017 resubmitted: 16 August 2018
- Date of referendum: 11 July 2019
- Website
- Pre-draft plan stage
- Regulation 14 draft plan stage
-
Bosbury and Coddington Group Parish Council submitted their draft Neighbourhood Development Plan to Herefordshire Council on 18 December 2014.
The consultation ran from 18 December to 12 February 2014.
- Regulation 16 plan stage
-
Bosbury and Coddington Group Parish Council submitted their Neighbourhood Development Plan to Herefordshire Council on 6 March 2015.
The consultation ran from 14 May to 25 June 2015.
Bosbury and Coddington Group Parish Council formally withdrew these plans on 9 November 2016.
- Regulation 16 plan re-submission stage
-
Bosbury and Coddington Group Parish Council re-submitted their Neighbourhood Development Plan to Herefordshire Council on 9 November 2016.
The consultation ran from 16 November 2016 to 11 January 2017.
- Neighbourhood Development Plan October 2016
- Bosbury parish policies map - resubmission
- Bosbury village policies map - resubmission
- Environmental report October 2016
- Consultation statement - resubmission
- Basic conditions statement - resubmission
- Regulation 16 consultation site notice - resubmission
- Representations received during submission consultation
- Regulation 16 plan second re-submission stage
-
Bosbury and Coddington Group Parish Council re-submitted their Neighbourhood Development Plan to Herefordshire Council on 8 June 2018.
The consultation ran from 15 June to 27 July 2018.
- Examination stage
-
The Bosbury Neighbourhood Development Plan was sent for examination on 17 January 2017. The examiner's report was received on 16 March 2017.
- Re-examination stage
-
The Bosbury Neighbourhood Development Plan was sent for re-examination on 16 August 2018. The examiner's report was received on 4 April 2019.
- Progress to examination
- Parish Council responses to regulation 16 comments
- Information note from independent examiner
- Information note regarding the new National Planning Policy Framework (NPPF)
- Information note regarding new basic condition
- Questions from the examiner
- Responses to examiner's questions
- Examiner's report April 2019
- Delegated decision document
- Referendum stage
-
The referendum for voters within the Bosbury and Coddington Group parish area was held on 11 July 2019.
- Adoption stage
-
The Bosbury & Catley Neighbourhood Development Plan was made on 16 August 2019. It now forms part of the Development Plan for Herefordshire.